HEI Telecommunications
CAMPUS INSTALLS

West Capital Complex
2206 Cerrilos Road
Santa Fe, New Mexico  

 

West Capital Complex project was a yearlong calibration with the Office of Communication, Fujitsu, and HEI.  It began with the installation of an 8’x 10’ x 8’ underground cable vault at one end of the campus and an 8,100 pair capacities cross-connect pedestal at the other.  HEI personnel did all concrete work for the pedestal placement, backhoe, and fill for the conduit paths between which 4” PVC conduits were installed linking the two locations.  A 1,800 pair cable was installed between the two points.  A 200 pair telephone cable was installed to State Personnel, which set the path for the next phase.  Each building on the campus was re-feed through the new cables to the cross-connect to allow for the future plan of removing the existing building to houses the campus wire pathways (the warehouse).  Cable cuts were done after hours on weekends to insure no disruption of service.  600 pair cable that services the MADD Building, 200 pair to T-187, 200 to State Personnel, and 300 pair to Library and Archives.  Office of Communications, Fujitsu, and HEI coordinated each cut.  All cables were restored with no report of downtime.  The campus also received a new fiber optic cable infrastructure to each of the three buildings.  This included all fiber termination and fiber distribution boxes in the install.

North Capital Complex
Downtown Santa Fe

HEI install fiber optic cable from the Education Building to five State buildings including Round House, PERA, Lew Wallace, Lamy and State Land Office.  The install included install 4-4” conduits across Don Gaspar from a manhole to the Education Building into the main switch room.  HEI coordinated with the City of Santa Fe for the closing of the street and was able to minimize the closing by working off-hours to complete the install. Nine manholes had to accessed in order to install the fiber optic cable to each of the buildings.  HEI had teams at each point to insure a smooth install and no damage to any of the cables throughout the install.  

State of New Mexico Office of Cultural Affairs  
228 E. Palace Ave.
Santa Fe, New Mexico  87503
 

This project linked five Museum Buildings in the Santa Fe downtown area to a central telecom closet in a sixth building with fiber optic cable.  The uniqueness of the Historical Buildings presented their own challenges. Each building was installed with wall-mount racks, fiber distribution boxes and SC connectors.  This will allow easy expansion of the new network that was to follow.

State of New Mexico
Office of Communications

1220 South St. Francis
Santa Fe, New Mexico
Pinon Project began the week before Thanksgiving and within three weeks of the project continuity was complete on the cables.  One 600 pair telephone cable and one 12-fiber optic cable were installed.  This connected the Pinon Building to the State Systems at the Simms Building.  To do this we installed four 4” conduits from the existing tunnel exit at the Lujan Building and trenched to the Pinon Building. Extending those four 4” conduits at the Pinon Building to the 2nd floor telecom closet and across the basement of the Simms Building where the exit of the tunnel is. The cables were installed in the conduit and through the existing tunnel system, approximately 3,000 feet.  An extension of cable tray in the tunnel completed the path.  This conduit system will allow any future expansion of the campus.   All terminations were completed with lightening protection for the voice and SC connections for the fiber.  A disc was provided of the wire map of all 600 pair cables as well as the dB loss of the fiber. All parking lot asphalt repairs were completed as well as walls and concrete pathways.

South Campus  
715 Alta Vista
Santa Fe, New Mexico

This project linked each building back to the Simms main computer room.  HEI install fiber optic cable from the Montoya, Lujan, and Runnels Building through the existing tunnel system throughout the campus.  All fiber was terminated with SC connectors and fiber distribution boxes were provided at each end.  HEI was able to install all fiber with no splice points.